PROJEK BEKALAN AIR TRIANG, BERA, PAHANG

Rancangan Bekalan Air Triang (Pakej 1, Pakej 2, Pakej 3, Pakej 4 & Pakej 5) – Membina dan Menyiapkan Loji Air Baru Triang dan Kerja-kerja Lain Berkaitan Di Triang, Bera, Pahang

Scope of Works:

  • Study of Triang Water Demand till the year 2020 Detailed Design of New 36 MLD Water Treatment Plant including the intake works. Detailed design of distribution mains and balancing reservoirs

Commencement: 1999
Completion: 2005
Contract Value: RM38.7 Million
Client: Pengurusan Air Pahang (previously known as Jabatan Bekalan Air Pahang)